KSEBL - Cost data of Distribution works - 2020

SI No.

Description of the work

Rate approved by KSERC in Rupees

1

LT single phase weather proof service connection upto and including 5kW  ( using  static meter with LCD facility)

1740.00

2

LT three phase weather proof service connection up to and including 10 KW  ( using  static meter with LCD display and TOD facility)

4220.00

3

LT three phase weather proof service connection above 10kW upto and including 25kW ( using  static meter with LCD display and TOD facility)

14420.00

4

LT three phase weather proof service connection above 25kW& below  50kVA

21750.00

5

LT three phase weather proof service connection from  50kVA and above upto and including 100kVA  .

23000.00

6

providing  support pole for weather proof service connection.

5540.00

7

LT single phase over head service connection upto and including 50m with max. 1 Post

9160+80per M of OH line

8

LT single phase over head service connection above 50 m upto and including 100 m with max.  2 Posts

21950+80 per M of OH line above 50m

9

LT single phase over head service connection above 100m up to and including 150m with max.  3 Posts

34450+80 per M of OH line above 100m

10

LT single phase over head service connection above 150m up to and including 200m with max.  4 Posts

46750+80 per M of OH line above150m

11

LT three phase over head service connection upto and including 50m with max. 1 Post

11550+160 per M of OH line

12

LT three phase over head service connection above 50m upto and including 100m with max.  2 Posts

28880+160 per M of OH lineabove 50m

13

LT three phase over head service connection above 100m up to and including 150m with max. 3 Posts

46600+160 per M of OH line above 100m

14

LT three phase over head service connection above 150m up to and including 200m with max. 4 Posts

64100+160 per M of OH line above1 50m

15

Post insertion for LT single phase over head line   (without stay)

6700

16

Post insertion for LT single phase over head line  (with stay)

8170

17

Post insertion for LT single phase over head line  (with strut)

13200

18

Post insertion for LT three phase over head line (without stay)

7730

19

Post insertion for LT three phase over head line (with stay)

9200

20

Post insertion for LT three phase over head line (with strut)

13850

21

Conversion of LT single phase weatherproof service connection  to LT three phase weather proof service connection  with connected load upto and including 10kW

4170

22

Conversion of LT single phase weatherproof service connection  to LT three phase weather proof service connection  with  load above 10 kW up to and including 25kW

15450

23

Conversion of LT single phase weatherproof service connection  to LT three phase weather proof service connection  with load above 25kW and below 50kVA

22800

24

Conversion of LT single phase weatherproof service connection  to LT three phase weather proof service connection  with load  50kVA and above up to and including 100kVA

23800

25

Enhancement of  connected load of LT three phase weather proof service connection with a max. load of  10kW into  the range of 10 kW to 25 kW.

14550

26

Enhancement of connected load  of LT three phase weather proof service connection with a maximum connected load of 10 kW into the range of 25 kW  to 50 kVA.

22550

27

Enhancement of connected load of LT three phase  service connection with a maximum connected load of  10 kW  into the range of  50 kVA to 100 kVA .

24550

28

Enhancement of connected load of LT three phase  service connection with  load  in the range of  10kW - 25 kW into the range 25 kW  - 50kVA

21210

29

Enhancement of connected load of  LT three Phase  service connection  with load in the range of  10kW -  25 kW  into the range of   50 kVA -100 kVA

22510

30

Enhancement of connected load of  LT three Phase  service connection  with load in the range of  25kW -  50 kVA into the range of     50 kVA -100 kVA

19510

31

Shifting   Single Phase Energy Meters

610

32

Shifting  Three Phase  EnergyMeters

800

33

Shifting  Three Phase CT Meters

1400

34

HT  pole insertion in HT/LT  line (with stay )

15870

35

HT  pole insertion in HT/LT  line (with strut using 8m pole )

17850

36

Providing strut using LT pole

6500

37

Providing strut  using HT pole

9100

38

Providing LT stay

1750

39

Providing HT stay

2310

40

Recondutoring LT line ,with Rabbit 1 conductor

55

41

Recondutoring HT line ,with Raccoon

240

42

Recondutoring HT line ,with Rabbit

170

43

Adding one conductor (ACSR Rabbit) on the existing poles (where cross arm is available) inclusive of cost of pin,insulator  etc.

85

44

Adding one conductor (ACSR Rabbit) on the existing poles (where cross arm is not available) inclusive of cost of pin, insulator  etc.

100

45

Conversion of LT single phase 2 wire line to LT Three phase 4 wire line (per metre)

165

46

Conversion of LT single phase 2 wire line to LT Three phase 5 wire line

215

47

Conversion of LT single phase 3 wire line to LT Three phase 5 wire line

165

48

Drawing Single Phase 2 wire line under existing HT line

130

49

Drawing Single Phase 3 wire line under existing HT line

200

50

Drawing Three Phase 4 wire line under existing HT line

250

51

Drawing Three Phase 5 wire line under existing HT line

310

52

Construction of LT single phase, 2 wire line

340

53

Construction of LT single phase, 3 wire line

400

54

Construction of LT 3 phase, 4 wire line

460

55

Construction of LT  3 phase, 5 wire line

520

56

Construction of 1Km of 11KV line using ACSR Rabbit (with out  tree cutting compensation )

605

57

Construction of 1Km of 11KV line using ACSR Racoon (with out tree cutting compensation ) using 24 no of poles and 21nos of stays

670

58

Laying 1KM of  HT XLPE  UG Cable (3x300 mm2 single run)

1770

59

Construction of 1 Km of  11KV line using ACSR Racoon with A Pole (with out  tree cutting compensation )

960

60

Construction of 1Km of  11KV line using ACSR Racoon with 4 Legged tower (with out  provision for  tree cutting compensation )

1880

61

Installation of 1 No. 11 KV/ 433 V , 25 KVA  Transformer

282000

62

Installation of 1 No. 11 KV/ 433 V , 100 KVA  Transformer   without stay( pole mounted )

390000

63

Installation of 1 No. 11 KV/ 433 V , 160 KVA  Transformer  without stay  (pole mounted)

547000

64

Installation of 11KV/433V 250 KVA Transformer  without stay

561000

65

Installation of 1 No.11 KV/ 433 V , 500 KVA, Transformer

874000

66

Installation of Data Acquisition  compatible Extensible type  Ring
Main Unit   without VCB -CCC (E)     (Cable -Cable -Cable )

425350

67

Installation of Data Acquisition  compatible Extensible type  Ring Main Unit   with VCB -CTC (E)   (Cable -Transformer -Cable )

482000

68

Installation of Data Acquisition compatible Extensible add-on type Ring Main Unit   without VCB  (Single Switch C-Extension)

371500

69

Installation of Data Acquisition compatible, Extensible, add-on type Ring Main Unit   with VCB  (Single Switch T-Extension)

443700

70

Installation of Data Acquisition compatible Extensible  type  Ring Main Unit   with provision for isolation and earthing facility  on both sides (GCG)

338000

71

Drawing 1Km of 11 kV  ABC of size 3X150 + 1X120 sqmm on 9 mts supports with an average span of 20-25 mts

1340213.03

72

Ddrawing 1Km of 11 kV ABC of size 3X120 + 1X95 on 9 mts supports with an average span of 20-25 mts

1197653.03

73

Drawing 1Km of 11  kV  ABC of size 3X95 + 1X70 on 9 mts supports with an average span of 20-25 mts

1156073.03

74

Drawing 1Km of LT ABC of size 3X95 + 1X70 +1X16 on 8 mts supports with an average span of 20-25 mts

883334.27

75

Ddrawing 1Km of LT ABC of size 3X70 + 1X50 +1X16 on 8 mts supports with an average span of 20-25 mts

841754.27

76

Drawing 1Km of LT ABC of size 3X50 + 1X35 +1X16 on 8 mts supports with an average span of 20-25 mts

794894.27

Note : GST will be collected extra as per rules applicable