KSEB Electricity Charges (ToD Tariff) for LT, HT & EHT Industrial consumers with connected load above 20KW

ToD Tariff applicable to EHT, HT and LT industrial consumers (with connected load of and above 20KW) Consumers

The  ToD  tariff  applicable  to  EHT,  HT  and  LT  industrial  consumers  (with connected load of and above 20 kW) for energy consumption is given below:

 

Rates

 

Normal period
(6:00 hrs to
18:00 hrs)

Peak period
(18:00 hrs to
22:00 Hrs)

Off peak (22:00 hrs to 6:00 hrs)

Energy Charges

100%

150%

75%

Billing of the demand charges:
Monthly Demand Charge shall be:
Billing Demand during the month x Demand Charge per kVA

Billing of Energy charges:
The billing of the energy charge for HT&EHT consumers shall be done as follows

a) Normal time: Consumption during normal time x energy rate / unit.
b) Peak time:     Consumption during peak time x energy rate / unit x 1.50
c) Off-peak time: Consumption during off-peak time x energy rate/unit x 0.75

Total energy charge during a month = (a) + (b) + (c)

Other conditions:

  • Demand/energy  charges  shall  be  the  demand/energy  charges  for  normal period as per the tariff approved in this Schedule.
  • Demand/energy charges  for LT industrial consumers with a connected load of and above 20KW, shall be as per the tariff approved in this Schedule.
  • Demand charges during a particular month shall be assessed based on the recorded maximum demand during that month or 75% of the contract demand whichever is higher.
  • Excess demand charges:  Additional  demand charges shall be levied if  the recorded maximum demand exceeds the contract demand during normal period and peak period, which shall be charged at 50% extra for the excess over the contract demand (ie., additional  demand during normal/peak period x ruling demand charges x 0.5).  Additional demand charges during off-peak period shall be levied only if the recorded maximum demand during off peak period is in excess of 130% of the contract demand.
  • For the consumption of electricity during normal period ie 6.00 hours to 18.00 hours the demand/energy charges shall be at the notified rates applicable to the consumer category.



Views: 120.